Case study

Substructure for a new build plot

Foundation walls, membrane and below-slab drainage for a new build.

Substructure with blue membrane laid and orange drainage pipes coming through the slab area

The challenge

The substructure had to be built up to damp course level, with the drainage brought through in the right positions before the slab was formed.

How we delivered it

  1. Stage 1: Substructure walls

    Brick and block foundation walls were built up to damp course level.

    Brick and block foundation walls built up to damp course level on a new plot
  2. Stage 2: Membrane and drainage

    The membrane was laid, with drainage brought through ready for the slab.

    Substructure with blue membrane laid and orange drainage pipes coming through the slab area

The result

A substructure ready for the slab and the trades that follow.

About our new build developments work
Typical section: Strip foundations and drainage to a new build. Strip foundations, Ground floor slab, Foul drainage to the sewer.TopsoilClaySand and gravelBearing stratum -1.0-2.0-3.0-4.0metresGL±0.00123

Key

  1. Strip foundations
  2. Ground floor slab
  3. Foul drainage to the sewer

Section A-A

Strip foundations and drainage to a new build

Scale

NTS

Typical section: new build developments. Indicative, not to scale.